Production has work center assigned in its production route that belongs to different sites

The error "Production has work center assigned in its production route that belongs to different sites" in Microsoft Dynamics AX 2009 typically occurs when a work center in a production route is assigned to a different site than the production order's assigned site. To resolve this issue, follow these steps: Step 1: Verify Production Route Setup Go to the production order where you're encountering the error. Path: Production Control > Common > Production orders > All production orders . Open the production order and navigate to the Route tab. Review the work center (Resource) assigned in each operation of the production route. Confirm that the work centers are assigned to the same site as the production order. Step 2: Check Work Center Site Assignment Go to the Work Centers (Resources) in the setup. Path: Basic > Common Forms > Resources > Work Centers (or similar depending on your module configuration). Find the work centers used in the prod